This paper discusses six major changes in AIA 201 (1997 version). These changes include: 1) Increased design delegation to the Contractor, 2) Mutual Waiver of Consequential Damages 3) Change in Indemnity Provision 4) Broader definition of Hazardous Materials 5) Requirement of Mediation and 6) Changes to Insurance.